Agoracom Blog

Xali Gold $XGC.ca: Permits Applied for Mexico Mines Tailings Project $FMG.ca $MEX.ca $AGI.ca $DSV.ca

Posted by AGORACOM at 8:31 AM on Tuesday, April 13th, 2021

Xali Gold Corp.(TSXV:XGC) (“Xali Gold” and/or the “Company”) is pleased to advise that permit applications have been submitted for the Mexico Mines Tailings Project in El Oro, Mexico. The permits are to allow both the transportation and re-processing of the Mexico Mine tailings at a new plant site located just 5 kilometers from the current location. Sun River Gold “SRG” and their Mexican subsidiary, Remediacion Rio Sol “RRS”, will be conducting all of the work on the tailings as part of an option agreement to acquire the Tailings Project and Xali Gold’s subsidiary, Minera CCM El Oro Jales.

A land package comprising 25 hectares has been purchased for the new plant site and the re-processing plant is expected to be operational within 12 months from receiving permits. Extensive laboratory testing has been performed, which was critical in completing design work for the plant and preparing detailed planning documents.

“We are very excited with the work that SRG has completed to advance the Tailings Project,” says Joanne Freeze, President and CEO of Xali Gold. “There have been some delays due to government closures during the COVID pandemic, but the project is now moving forward and we are very excited to the re-processing getting into operation.”

In addition to laboratory test work, SRG has also completed the following work in preparation for the operation:

  • Design of the plant site
  • Mine plan of tailings indicating extraction levels over the years
  • Developed a contour map demonstrating resulting topography of municipal land once tailings are removed
  • Engaged power contractor to upgrade and extend power lines to site
  • Secured access across private land for roads and power lines
  • Secured access to water from local sources

Xali Gold’s subsidiary, CCM El Oro Jales, has an agreement with the municipality of El Oro which provides the Company the right to recover all available gold and silver from the Mexico Mines tailings deposit and pay to the Municipality of El Oro an 8% Net Profits Interest (“NPI”). Xali Gold will also retain the first US$1.5M from the 8% NPI payable to the Municipality.

SRG has the option to acquire 100% of the Tailings Project by making staged payments totalling US$500,000 (paid), bringing the tailings into commercial production within 36 months of the effective date of the option agreement, and granting to the Company a 5% NPI, Life of Mine royalty as well as the Municipalities 8% NPI on production from the properties. The 36 month term has been extended for 6 months providing that SRG demonstrates sufficient progress during each 3 month period.

Read More: https://agoracom.com/ir/XaliGold/forums/discussion/topics/758945-permits-applied-for-mexico-mines-tailings-project/messages/2311722#message

Tags: , , , , , , ,